State Grid Xinjiang Electric Power completes a pilot program for valley-filling demand response.
State Grid Xinjiang Electric Power completed a pilot program for valley-filling demand response in the southern Xinjiang region, launched on July 20 and covering Kashgar, Kizilsu, and Hotan. The pilot achieved 376 response events, totaling 5.1166 million kWh with a 100.28% execution rate, and a maximum daily response load of 77.4 MW.

Key facts
- 01Pilot started on July 20 and covers Kashgar, Kizilsu, and Hotan commercial and industrial electricity users.
- 02Total of 376 valley-filling demand response events; effective response energy 5.1166 million kWh; execution rate 100.28%.
- 03Maximum single-day response load reached 77.4 MW; maximum single response energy 386,800 kWh.
- 04Digitalized chain of invitation–response–monitoring implemented via the new load management system and Online State Grid app.
- 05The pilot demonstrates flexible demand-side adjustment for high-penetration renewable energy and aims to expand nationwide in Xinjiang.
AI-generated from the sources below. Always check the originals.
How each country tells it
So far one country has covered this event. Perspectives appear when media in a second country report it.
Sources
Summaries are AI-generated from the linked sources and may contain errors; always check the originals. We summarise and link; we never republish articles. Photos come from openly licensed libraries, official publicity material and brand logos, credited to their sources. If you own an image and want it credited differently or removed, email info@coda.news and we will act promptly.
- 新疆首次填谷需求响应试点收官 创新负荷调节模式助力绿电消纳 · 中国新闻网